- Culverts
- 2 days of work
- Water and air supplied by general contractor
Lined 11′ x 75′ corrugated culvert pipe with 2″ of ML_72 Microsilica Restoration Mortar.
Categories : |
Recent Projects
|
---|
- Culvert
- 3 days of work
- Water supplied by city “fire hydrant”
- Coordination with Railroad
Lined 3′ x 102′ brick culvert with ML-72 Microsilica Restoration Mortar.
2 days of prep were needed to clean culvert properly for material to work properly. Day 3 we lined the culvert and the general contractor was able to keep going on project with a minor delay. We had to coordinate all of our activities with the BNSF railroad during the whole project to allow for no shut downs for Railroad on this project,
Categories : |
Recent Projects
|
---|
Mound, MN
133 VF Manhole Lining
32 Int. Chimney Seals
Categories : |
Recent Projects
|
---|
- Culverts
Lined two 48” ID X 244’ L CMP culverts by prepping and spin casting with 2” thick ML-72 Microsilica Restoration Mortar. This non-destructive method saved the city over 30% from the Engineers estimate. We also rehabbed 3 sanitary sewers (18 VF) with ML-72, as long as we were there!
Categories : |
Recent Projects
|
---|
- Owatonna, MN
- 54 VF
- MH Rehab
Rehab six old brick manholes downtown by patching large voids, plug leaks and coating with 1” thick ML-72 Microsilica Restoration Mortar to restore structural integrity and extend the lifespan. Eliminated the costly and disruptive need to dig and replace.
Categories : |
Recent Projects
|
---|
- Winona, MN
- 32 VF
- MH Rehab
Restore to like new condition four old brick manholes. We used ML-10 Hydraulic Cement to patch large voids, repair inverts and patch pipes . Then coated with 1.5 inches of ML-72 Microsilica Restoration Mortar. The before and after pictures are impressive!
Categories : |
Recent Projects
|
---|
- Orono, MN
- 120 VF
- MH Rehab
Proactive rehab of 32 precast manholes. Invert reconstruction, patch, seal, injection grout and spin cast 1” thick ML-72 Microsilica Restoration Mortar, install internal chimney seals as specified.
Categories : |
Recent Projects
|
---|
- Windom, MN
- 25 MR Manhole
- Set Casting, poured concrete
- 15 Water Box
- Set Water Box, poured concrete
2020 Street Reconstruction Project let us showcase the Mr. Manhole Leveling System as we came in AFTER THE PAVING WAS DONE and set and installed 25 manholes and 20 water valves. This saved the paver and general contractors valuable time and money.
Categories : |
Recent Projects
|
---|
- Crystal, MN
- 34 Ext. Chimney Seals
- Cut 14″ Assphalt & Concrete
- Reset Castings, Poured Concrete
Cut, pulled, replaced and set 30 manhole castings on busy Bass Lake Road.
Categories : |
Recent Projects
|
---|
Avonti grouted a 13′ manhole around the 2′ invert and also stopped pouring water penetrating into the 12″ flow line exiting the manhole.
Categories : |
geotechnical
|
---|
Avanti grouted a 13′ manhole around the barrel joint near the bench, also grouted around the invers.
Categories : |
Water & Waste water
|
---|
Avanti grouted around 8″ & 12″ pipes in a Air Vault. We sealed up 5 of these that all leaked water into vaults roughly 8′ x 8′ x 7′ deep
Categories : |
Water & Waste water
|
---|
Avanti grouted the floor in the tunnel under the street for the school. Tunnel was 12′ wide by 150′ long. Tunnel floor is below water table, so hydration was a major issue.
Categories : |
geotechnical
|
---|
Fixed a major leak at a new wastewater treatment facility. The probes we pushed into the ground 18′ to 20′ down, then inserted grout and stopped the major leak
Categories : |
Water & Waste water
|
---|
Chemical grouted around 3 pipe inverts and sealed up 2 barrel joints in this Lift Station. Had little time to shut down this lift station and monitored the levels as we had to shut off lift station to work inside. We were in and out in 1.5 hrs and sealed up some major active leaks!
Categories : |
Water & Waste water
|
---|
Chemical grouted 9 Manholes throughout town. We focused on the barrel joints and the benches where water was actively pouring in around the inverts. Some of the Manholes were in wet areas in the grass and in the backyards of houses making it difficult, but we know from experience what it takes to get the job done!
Categories : |
Water & Waste water
|
---|